BPA Ltd - architectural, festive and environmental lighting specialists


Limehouse Cut Lighting Scheme; Commercial Road Underbridge & Towpath Scheme



Technical and Maintenance

Equipment used: Nine 1.2 watt LED projectors for the offside, together with seven 18 watt compact fluorescent bricklights for the towpath. We installed, and arranged for connection of, a new street feeder pillar to provide power as there was no suitable existing supply at towpath level.

Approximate running costs: Assuming an electricity supply price of 10p per kilowatt hour then 1.5 per hour giving an annual running cost of £70 based on an average burning time of 12 hours per day. Two year re-lamping and cleaning cycle.

 Description 